One9, Hall Street Moonee Ponds, 34 apartments, 5 days

Rome may not have been built in a day but One9 Hall Street apartments almost were....oversimplifying it yes, yet locals within visual range of the Moonee Ponds apartment project stood agog as 34 prefabricated apartments were delivered and erected within five days in spectacular fashion.

For those readers unaware the prefabricated apartment system championed by Hickory Group is known as Unitised Building, and "is a structural building technology which accelerates onsite and offsite construction programs by up to 50%, minimising material and energy waste, whilst maximising quality and safety.  It brings the best of automotive manufacturing technology, systems and processes into the construction industry. 

Further, "Unlike other modular construction products available on the Australian market, Hickory units are not made to a set size or layout. They can adapt to any architectural design and scale, and are factory-finished to completion, including the building façade. They also have no theoretical height limitation."
 
 
According to Hickory Group, the key benefits of the modular construction system are:
• Up to 50% faster construction programme
• 90% less disruption to local community during construction
• 60% reduction in transport energy
• 90% less construction waste than a comparably sized in-situ construction
• Over 90% of waste produced is then recycled
• 15% less embodied energy over the lifecycle of the building
• 75% lighter structure, can be used on ‘unbuildable’ sites that would withstand the weight of a conventional build
• Safer work environment – facades attached in factory eliminating work at height on the live edge of the building
 
As evidenced below the inherent beauty of the Unitised Building system is that all modular units are delivered by way of truck to site with near all appointments included.  Tiled balconies, split system units, kitchenettes etc are all installed and complete with final plumbing and electrical services required to bring the modular units to occupancy standards.  Certain units also carried ancillary materials such as plasterboard to commence internal fitout of the precast concrete structure.
 
 
Under the guidance of head contactor Vaughan Constructions, site preparation works began during May with fabrication of the modular units concurrently occurring offsite within a dedicated Brooklyn line fabrication facility, culminating with a five day onsite assembly which commenced last Thursday.  No stranger to Urban Melbourne after lifting train carriages atop the End To End office development in Collingwood, Metcalf Cranes Terex Demag AC350 was once more charged with lifting an unusual load. 
 
As with operations of this magnitude much planning had been placed toward transport and traffic considerations.  Cardno Group after discussions with Moonee Valley City Council sectioned off parts of busy Moonee Ponds Junction, acting as a holding bay while FTW Group delivered unit after unit via the path of least resistance, that being suburban Buckley Street, Essendon.
 
Testament to all parties involved that the delivery and erection of a nine level building over five days occurred in a safe and timely manner, with little fuss and minimal public disruption.
 

Unsurprisingly this article appears under Urban Melbourne's ESD category as Hickory Group believe Unitised Building to be environmentally friendly, practically sustainable whilst also representing a quantum leap forward in design and delivery methods.  And here's a though to leave you with.  Given Hickory Group have identified synergies between the efficiencies of automotive line production and that of Unitised Building's production, should Victoria's ailing automotive industry flatline, could a percentile of automotive industry workers find salvation in some way, shape or form via an expanded Unitised Building assembly line in the future?

But that of course is a topic for another day.  See below a sequence of images taken over the five day assembly period.

Thursday - initial unit lowered into place
Rate this article: 
Average: 5 (4 votes)

Comments

Chris Peska's picture

Fantastic example of the number of benefits associated with unitised building. For the purposes of comparison, how long would One9 take to build using a conventional construction method?

Observe. Design. Build. Live.

Alastair Taylor's picture

Here's a tweet diary of the weekend's events

 

Friday:

Saturday:

What it's going to look like:

Sunday

Monday

Development & Planning

Thursday, April 17, 2014 - 06:46
Last week project partners celebrated the official start to works for Dandenong's new ATO complex, which spearheads an increased level of development in Melbourne's 'second city'. At the on-site ceremony EPC Pacific Chief Executive Patrick Smith stated “This development is achieving the vision of the Revitalising Central Dandenong project by...

Policy, Culture & Opinion

Friday, April 11, 2014 - 12:00
Height is perhaps the most contentious of all issues when discussing new building proposals. Maybe because it is readily quantifiable relative to the surroundings, or because fear of height has become a default response to any new development, it is often debated as a singular issue. Many ignore the other...

Advertisement

Visual Melbourne

Wednesday, April 2, 2014 - 13:56
Do you have an Instagram account? Do you like taking photos of buildings? Would you like to win a $500 voucher to dine on some top nosh? Well, follow @Elenberg_fraser on Instagram, take original photos of EF designed buildings, tag the EF Instagram account in your photo and use the...

Transport & Design

Saturday, April 19, 2014 - 07:14
"Reimagine. To reimagine is to do something in a way that's never been done before." That's the crux of Emporium Melbourne 's new marketing campaign that ushered in the opening of the new $1.16 billion retail project on Thursday. It's been a while coming, in fact far longer than the...

Sustainability & Environment

Image © tensile.com.au
Thursday, April 3, 2014 - 12:05
Last week the Australian arm of prominent global engineering firm Meinhardt released a white paper titled 'How Far Are We From Truly Green Façades?' via their Practical Imagination platform. The white paper delves into the issues currently surrounding the advancement of green facades which in turn allows the practice to...